Significant progress continues on the restoration of the Chesterfield Canal at Staveley, one of the projects within the Staveley Town Deal.

The restoration will reconnect key sections, protect historic features, and create new opportunities for leisure, tourism, and economic growth. The Chesterfield Canal Trust is leading the main phase of restoration works, supported by £5.8 million of the Staveley Town Deal.

Contractor O’Brien Construction Ltd is delivering the main phase of works on the Chesterfield Canal, which includes:

    • Construction of the new Keith Ayling Lock
    • Installation of a water pumping system designed to allow fish and eel passage,
    • Restoration of Bellhouse Basin, including its historic narrows,
    • Reinstatement of the canal through the Hartington Railway Bridge abutments
    • Upgrading footpaths between Bent Lane and Bellhouse Lane
    • Installation of new benches, interpretation panels and extensive landscaping

By restoring navigability and improving surrounding infrastructure, the project will help to encourage an increase in visitor numbers to Staveley, supporting local businesses and tourism as well as enhancing public spaces, including footpaths, bridges and green areas, having an overall impact on improving the quality of life for residents through better access, recreation and employment opportunities.

Over the past months, visible progress has been made on the site. Towards the end of November, the lock excavation was completed, followed by extensive rebar installation and concrete pours throughout early December.

Staveley Town deal

By mid-December, the base slab for the Keith Ayling Lock had been completed, clearly showing how the restored basin will be raised to its final level. Historic stonework from Bellhouse Basin was carefully removed, labelled and stored, ready to be reinstated as part of the restoration.

Meanwhile, Severn Trent Water has been working alongside the project to lower a major 500mm water main beneath the restored canal at Bellhouse Basin, with this element expected to be completed by the end of the month.

The current completion date for the main works is mid-July, bringing Staveley another step closer to seeing the Chesterfield Canal fully restored through this key section.

The Staveley canal restoration is a powerful example of how the Staveley Town Deal is investing in heritage, infrastructure and community wellbeing, creating a destination that will support economic growth while celebrating the area’s industrial past.

For more information and to keep up to date with developments in and around our town, please visit: www.chesterfield.co.uk/developments/staveley/

Alex Baddley

Content Creator

Email Alex